GLS-16-July-2008

From GEANT2-JRA1 Wiki

Attendees

  • Nina Jeliazkowa
  • Nicolas Simar
  • Maciej GÅ‚owiak
  • Michael Bischoff
  • Szymon Trocha

Agenda

  1. API* status
    • Mostly done. Discovery works for eventTypes. Topology elements need some additional work to support different elements (to be done today)
    • Polishing of class names needed
    • Finalized this week
  2. psUI implementation status
    • Use of gLS ready for the demo in Berlin but rather linked to RRD MA
    • Incorporating API level0 should be quite easy while level1 and 2 needs investigation (e.g. if additional parsing is needed) of the code provided by MB
  3. gLS implementation status
    • Working with summarisation of IP addreses based on Martin's code and /32 and for domains.
    • Self-tests ready
    • Next RC on Thursday, 17 July
  4. Test infrastructure status
    • Ready with 4 hLS and 4 RRD MAs. Summarisation works but an issue with eXist. Still needs investigation. NS: look at eXist forums for some help
    • When a new RC is out re-install services
  5. Next steps
    • Covered in actions

Actions

Actions from previous conf calls - still some on-going there or not done

  • MB to finish API implementation this week and then let Nina now when it's done
  • NJ to investigate the complexity of APIs integration with psUI (when finished by MB)
  • ST to update Test_Infrastructure wiki page with working services needed for testing (for Sasa) - DONE - hLS test instance provided for Sasa. Still need to update Wiki
  • MG to provide a new gLS RC (including self-tests, IP summarisation) for Thursday, 17 July -DONE
  • All to use full domain names in metadata configuration files
  • ST to check the status of gLS tests doing by Prodromos - DONE - No answer received but Prodromos contacted directly with MG
  • MG to send information about the current content of gLS for 3.1 and what will be done in future with new pSbase - DONE
  • MG to send to NS where full domain names needs to be changed in metadata configuration file - DONE
  • ST to verify services documentation and specify where to configure full domain names - not done yet
  • MG to investigate MB's proposal of changes into eXist (sessions) - partially DONE - implemented but not investigated,
  • All - next call on Wednesday, 23 July 11:00 CEST, Skype