D1.4 Workplan

The workplan has been designed to match to the Prototype_workplan.

  • Report on data retrieval techniques (subtask 1.1.): final report due for March 31st.
    • Data extraction techniques - Data extraction methods to retrieve data from measurement points including SNMP, IPPM, flow tools, MAPI, BWCTL. Subtask 1.1. of D1.4.
  • Architectures evaluation (subtask 2) is performed by the Prototype design
  • Report on data archives (subtask 2): report provided by RedIRIS until March 24th
    • See also the prototype's DB comparison MySQL vs. PostgreSQL benchmark results - a comparsion of these two databases.
  • Data aggregation - See metric composition document
  • Measurement archive design (subtask 4): due until March 31st (see JRA1_D1.4_Database_Schema)
  • Guidelines for ergonomy/usability of user interfaces: due until mid May
  • Action plan for path visualisation tool